Project Description

Air Treatment Facility – Luggage Point Sewerage Treatment Plant.

Scope

Design, supply, install and commission a complete outdoor controls switchboard and associated local control stations. Time critical project.

Attributes

Complete Turnkey Contract.

Electrical and structural engineering works • Outdoor arc fault containment switchboard design and build • Cabling and ladders • Multi discipline project management.

Challenges

Designing for an aggressive H2S environment close to sewerage inlet works. • First application of an extended version of PTAS’s ABCD arc fault containment modular outdoor switchboard. • First application of new Siemens programmable controls. • First project under principal’s new management model.

Testimonial

  • PTAS met their timeline with a high quality project.
  • Relationships under new contracting model worked well.